Design and Procurement. This involves a site investigation, drilling into the ground to determine soil and rock formations where the turbine foundations will be placed, design of turbine foundations, Operations and Maintenance Building, electrical conductor routes, roads, securing permits such as Storm Water Pollution Prevention Plans, National Pollutant Discharge Elimination System, Building, Electrical, Utility Crossings, Gravel Pit, and Air Discharge for Gravel Crushing.

Construction. Overlapping design and procurement is the actual construction process. The first construction activities were clearing for the Operations and Maintenance Building and surrounding area where the construction contractors have located their offices and marshalling areas. In this vicinity work has also begun on the Project substation.

Road Construction. This involves road construction within the Project area and reinforcement of the local County roads leading to the site. Even though these are County roads, the reinforcement is for the purpose of the Project and thus paid for by the Project. Work has begun on the project roads and the bulk of the reinforcement of the local County roads has already been completed.

Crane Pad Construction. As soon as road construction has progressed sufficiently, foundation and crane pad construction will begin. Because the turbines are so large, 420 feet tall at the peak of the blade, a large level area is required for positioning the crane to lift the turbine components into place. The total lift capacity for this crane is 400 tons, which far exceeds the total weight of the turbine components, but is required due to height of the lifts involved.

Electrical Cable Installation. Follows road construction as all electrical cables from the turbines to the Project substation will be buried underground to eliminate air flow interference and minimize perching opportunities for birds within the Project boundary.

Turbine Delivery & Erection. After roads, foundations and underground cables are in place, cranes arrive to erect the turbines. The cranes are sufficiently large that they must be brought in pieces, a total of nine semi truck trailers per crane, and then assembled on site. Each turbine takes about two full days of crane time to erect.

Commissioning Crew Evaluation. Commissioning crews come in to complete all the electrical connections inside the towers and to "wring" out all of the various functions of the computer controls for each turbine. To fully evaluate the function of the turbine, commissioning crews must wait for windy conditions over fixed periods of time to ensure all systems are working properly.

Project Completion. As you can see from the schedule total time from initial road construction to final completion is expected to take just over one year.

Click to download a more detailed explanation of the timeline:
WhiteCreek_ConstructionSchedule.PDF